Combined Cycle Plant Baja California III Mexico Selects J&R

The installation and commissioning of JR101-FK-Y-HB analog phones in CC Baja California III

The installation and commissioning of JR101-FK-Y-HB analog phones in CC Baja California III

Full Name :Baja California III combined cycle plant

Project Type : Combined cycle

Development Phase :In operation

Project Status :Active

Project Capacity :308 MW (megawatt) Combined cycle

Investment :US$ 270mn

Completion Date :2017

Lifespan :25

Location: The Baja California III combined cycle plant is to be located 21.5km northeast of the city of Ensenada.

The Baja California III project calls for the construction and operation of a natural gas-fired combined cycle plant. Infrastructure needed includes gas and stream turbogenerators, a heat recovery system, transmission infrastructure and natural gas supply pipelines. The plant will inject power through the future 230kV SE-La Jovita substation in the Ensenada municipality.

At J&R, we produce Heavy Duty Telephones for emergency and industrial areas.

Our vision is based on a unified and consistent approach to delivering products that can interface with other communication systems, thereby reducing costs and eliminating inefficiencies of using proprietary and non-reusable solutions.

We constantly ensure that we are at the forefront of developments to deliver the very best communication devices for voice, and data .

we hope that this installation will be a good example for other generating plants project around the world.