Combined Cycle Plant Baja California III Mexico Selects J&R
The installation and commissioning of JR101-FK-Y-HB analog phones in CC Baja California III
The installation and commissioning of JR101-FK-Y-HB analog phones in CC Baja California III
Full Name :Baja California III combined cycle plant
Project Type : Combined cycle
Development Phase :In operation
Project Status :Active
Project Capacity :308 MW (megawatt) Combined cycle
Investment :US$ 270mn
Completion Date :2017
Lifespan :25
Location: The Baja California III combined cycle plant is to be located 21.5km northeast of the city of Ensenada.
The Baja California III project calls for the construction and operation of a natural gas-fired combined cycle plant. Infrastructure needed includes gas and stream turbogenerators, a heat recovery system, transmission infrastructure and natural gas supply pipelines. The plant will inject power through the future 230kV SE-La Jovita substation in the Ensenada municipality.
At J&R, we produce Heavy Duty Telephones for emergency and industrial areas.
Our vision is based on a unified and consistent approach to delivering products that can interface with other communication systems, thereby reducing costs and eliminating inefficiencies of using proprietary and non-reusable solutions.
We constantly ensure that we are at the forefront of developments to deliver the very best communication devices for voice, and data .
we hope that this installation will be a good example for other generating plants project around the world.