#Industry News
The Hidden Challenges for O&M Teams Shifting from Air Cooling to Liquid Cooling in Modern Data Centers
No Air Outlets, New Safety Intuition: Why O&M Habits Are the Hardest Part of the Liquid Cooling Shift
An eight-year air conditioning engineer instinctively looked for air outlets in a liquid cooling room—found none. The biggest hurdle for O&M teams is not technical skill but ingrained air-cooling habits. Coolant systems demand cost awareness: glycol testing and replacement cost thousands of dollars, while excessive flow reduces efficiency and raises energy use. Safety adds leak checks, coolant-electrical isolation and fire compatibility, and maintenance takes two to three times longer. At least three months of onsite practice is essential to build new safety intuition. EXTRCOOL offers dual-mode CDUs, manifold assemblies, cold plates, rear-door heat exchangers, dry coolers and containerized systems.