Flottweg Plant 2: Growing and Thriving

The new facility, built at a cost of 55.9 million USD, represents the single largest investment in our company's history.

Much has happened in the year since the first shovel went into the ground. Construction teams continue to pour foundations, prefab concrete walls, and erect columns that will enable installation of the steel roof beams

In November, the building (193,000 ft²) will be closed for additional interior work, with an official completion date set for the end of August 2020.

Despite the seven-week delay caused by Mother Nature, Project Manager Stefan Koniger says he is pleased with the construction progress to date: "The weather toward the end of last year gave us some headaches, but we have since been able to catch up. I'd like to thank our partners and my colleagues for their hard work, which has helped us get back on schedule." s that will enable installation of the steel roof beams