FAT finished 1 May 2018
On 1st of May 2018 FAT was finished. The equipment included a separator unit, a CIP-station 2x200 L and a 50 L freeze-dryer.
On the first day we checked the documentation for every piece of equipment, checked the equipment components presence and dimensions (for the CIP station and the freeze-dryer) and electric parts presence according to the P&ID (for the separator).
On the second day of FAT we did more tests:
- electrical wiring integration test for the CIP station and the freeze-dryer
- components integration test for the separator
- condencer cooling verification test for the freeze-dryer
- vacuum performance verification test for the freeze-dryer
On the third day of FAT we conducted the following tests:
- digital/analog i/o functional test and electrical safety integration test for the CIP station
- components integration test and electrical wiring integration test for the separator
- shelf temperature performance verification test and shelf heat-up rate & max temperature test for the freeze-dryer
On the 4th day of FAT we conducted the following tests:
- leakage test, control acceptance test and cleaning performance test for the CIP-station
- CIP coverage and SIP effectiveness test for the freeze-dryer
- electrical powers integration test, electrical safety integration test and spray cleaning acceptance test for the separator
On the 5th day of FAT the following tests were finished:
- ice condenser capacity and defrosting test for the freeze-dryer (it lasts 24 hours)
- digital/analog i/o functional test (separator)
From 30 April to 1 May we did leakage test, SIP test and control acceptance test for the separator and finished FAT on 1 May.