Non-standard bore sizes add 15-30% lead time, but the penalty varies by tooling proximity. Here is how to predict the delay before committing to a schedule.

The Non-Standard Bore Trap: Why Your "Standard" Lead Time Is Actually 8 Weeks

You just received a quote for a non-standard honed tube bore. The supplier quoted the price premium, but the lead time looks normal. You schedule production accordingly.

Weeks later, you discover the real timeline is double what you planned.

Here is the uncomfortable truth about non-standard bores: the price premium is roughly fixed, but the lead time penalty is not. Depending on how far your requested bore is from the supplier's existing tooling, that delay can vary by a factor of 2x to 3x:

Within 3mm of a standard size? Setup is quick (+3-5 days).

5-10mm off? Requires special honing stones (+1-2 weeks).

10-20mm off? Mandrel modification (+2-4 weeks).

Completely non-standard? New mandrel fabrication (+4-8 weeks).

The real trap? Most buyers ask, "What's the lead time for a 73mm bore?" The supplier quotes their standard timeline, silently omitting the setup time. The right question is: "Is 73mm in your standard tooling set, or does it require setup?"

There is also a critical distinction between first-order and repeat-order lead times. Once a supplier sets up the tooling, your second order runs at normal speed. If you don't plan for that first extended lead time, you will miss your production window.

Don't let a hidden setup delay derail your schedule. Read the full article to learn the 4 bore categories, how to ask the right question, and when substituting a standard bore size can save you weeks of lead time.