LOGO.3 in the precast reinforced concrete plant of Beton Tille GmbH & Co. KG

Regulated water flow with frame outlets made of precast reinforced concrete elements under rail tracks and a federal highway.

The infrastructure construction project with the coordinates 50.87286984204861, 8.763770114445407 (50°52'22.3"N 8°45'49.6"E) is currently one of the largest in the state of Hesse. The purpose of relocating the B 252 is to relieve traffic in the affected areas by 90%. The first section between Wetter and Großfelden has already been completed.

Further on in the course of the construction of the new B 252, in the Sarnau section, the Lahn cycle path, Federal Highway 62 and the railway line have to be relocated to make room for the new bypass. The RB 42 railway line between Marburg and Frankenberg was laid between Sarnau and Niederwetter over a length of around 600 meters and runs at around 30 meters' distance from its previous route.

This also required adjustments to the RB 94 railway line between the Sarnau train station and Sarnau.

For safe and targeted surface drainage, a frame passage made of precast reinforced concrete elements was laid under the railway lines from Biedenkopf to Sarnau, from Kreuztal to Colbe, the footpath and bike path and under the B 62 over a length of 62 m.

The production and delivery order for the construction project was placed with Beton Tille GmbH & Co. KG.

For this construction project as well, Managing Director Friedrich-Wilhelm Reineke also worked out a pragmatic solution proposal together with those involved in the construction, and rented formwork material from PASCHAL to implement the project.

Using 40 m² LOGO.3 wall formwork, with element dimensions 135 x 270 cm, 17 precast reinforced concrete elements were produced in the Beton Tille GmbH & Co. KG factory.

The longest frame passage element measures 7.00 m. In addition to the straight precast reinforced concrete elements, two 45° angle elements with an inspection entrance and two end elements with an incline for installation in the embankments were also manufactured.

Beton Tille GmbH & Co.KG used self-manufactured steel cores to produce the inner profiling. The external formwork consisting of LOGO.3 elements was precisely fixed using inclined supports and the C35/45-quality concrete that was poured in was compacted using internal vibrators. The front parts of the precast concrete elements were manufactured using the "tongue and groove principle" and to the specified tolerances. They serve to securely connect the elements among themselves.

Before installation, i.e., the process of pushing one element onto another, a self-adhesive squeeze joint tape was applied to the reveal.

“This application highlights the universal applicability of PASCHAL formwork systems. To supplement our factory formwork, the required formwork material was accessed from the PASCHAL rental park on short notice,” says Managing Director Friedrich-Wilhelm Reineke.

Beton Tille GmbH & Co. KG is an established precast concrete factory which has proven its efficiency and manufacturing quality across numerous projects. The precast concrete plant repeatedly uses rented equipment from PASCHAL for unusual and special solutions.

The wall formwork system LOGO.3 used at Beton Tille GmbH & Co. KG for forming frame passage elements.