Add to favorites

#Product Trends

Yet again, PASCHAL demonstrates total formwork expertise with the very latest of wind power systems

Very soon, two of the latest 6 MW generation of wind turbines will start operating at the Nortorf II wind farm. PASCHAL’s TTR trapezoidal girder formwork was used in their construction.

In future, this pair of wind turbines at the Nortorf wind farm will generate 13.2 MW, replacing four old wind turbines.

These two mega-wind turbines are the first of the new 5.X platform from Siemens Gamesa in Germany. They are scheduled to enter service in 2022. To enable one of the most powerful onshore wind power facilities in the world to deliver green electricity promptly, the gigantic and separate foundations for these two megawatt wind turbines were completed at the end of 2021.

The external diameter of a circular mast foundation measures 23.00 m. To ensure that load is transmitted into the substrate safely, piles were first driven down until they encountered a viable base layer.

To absorb the fulcrum forces around the perpendicular axis safely, additional load was applied to the steel-reinforced concrete foundations. To enclose the material used for this additional load, a steel-reinforced concrete wall measuring 30 cm in thickness had to be concreted in with an internal diameter of 22.40 m. To accomplish this, the construction company carrying out the work, Terraform GmbH, used TTR circular trapezoidal girder formwork with a formwork height of 1.50 + 0.37 m.

The circular trapezoidal girder formwork was pre-curved, then delivered in ready-to-use form to the construction site by B.B.F. Handels- und Vermietungs GmbH, PASCHAL’s commercial partner. Each enclosure could then have formwork installed and cemented in a single operation.

To enable the components of the turbine wheels to be installed, the cranes needed to have very robust base platforms as well as equally robust plots of land to support the gigantic counterweights. PASCHAL’s Modular/GE universal formwork was used to install the foundations for these service areas.

Very soon, two of the latest 6 MW generation of wind turbines will start operating at the Nortorf II wind farm. For this, PASCHAL's TTR trapezoidal girder formwork was used.

Details

  • Kreuzbühlstraße 5, 77790 Steinach, Germany
  • PASCHAL-Werk G. Maier GmbH

    Products associated